Considering driving 40 rft depth, 1.65 nos pile
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Hire charge of pre-cast pile driving complete rig set including operational expenses Hire charge of driving equipment with liner in/c cost of fuel and lubricant etc. | 1 | day | 6000 | per day | 6000 | 6000 | |
| 2 | Pile rig operator Rig operator | 1 | no. | 700 | per day | 700 | 700 | |
| 3 | Skilled labour Skilled labour | 2 | no. | 600 | per day | 600 | 1200 | |
| 4 | Ordinary labour Ordinary labour | 12 | no. | 550 | per day | 550 | 6600 | |
| Sub-Total | 14500 | |||||||
| Contractor's Profit | 10% | 0.1 | 1450 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 507.5 | |||||
| Total | 16457.5 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1334.39 | ||||
| Grand Total | 17791.89 | |||||||
| Rate per rft | 269.58 | |||||||
| Rate per per meter | 884.49 | |||||||