Extra rate for each additional 0.5 meter depth exceeding 1.5 meter Considering 1000 cft work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Ordinary labour Ordinary labour | 1.5 | nos | 550 | per day | 550 | 825 | |
| Sub-Total | 825 | |||||||
| Contractor's Profit | 10% | 0.1 | 82.5 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 28.88 | |||||
| Total | 936.38 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 75.92 | ||||
| Grand Total | 1012.3 | |||||||
| Rate per cft | 1.01 | |||||||
| Rate per per cum | 35.67 | |||||||