Breakup

02.1.6 Added rate for each additional 0.5 meter depth exceeding 1.5 meter.

Extra rate for each additional 0.5 meter depth exceeding 1.5 meter Considering 1000 cft work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Ordinary labour Ordinary labour 1.5 nos 550 per day 550 825
Sub-Total 825
Contractor's Profit 10% 0.1 82.5
Contractor's Overhead Expenses 3.5% 0.035 28.88
Total 936.38
Add VAT with adjustment factor. 1.08108 7.5% 0.075 75.92
Grand Total 1012.3
Rate per cft 1.01
Rate per per cum 35.67