Mobilization and demobilzation of automatic diesel hammer mounted complete rig set.
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Truck fare for carrying diesel hammer mounted rig Truck fare (2 x 5 trips) in/c loading & unloading | 10 | trips | 15200 | per trip | 15200 | 152000 | |
| Sub-Total | 152000 | |||||||
| Contractor's Profit | 10% | 0.1 | 15200 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 5320 | |||||
| Total | 172520 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 13988.09 | ||||
| Grand Total | 186508.09 | |||||||
| Rate per set | 186508 | |||||||
| Rate per per set per site | 186508 | |||||||