Breakup

09.19 Driving 300 mm x 300 mm & 350 mm x 350 mm size pre-cast pile by rig fitted with automatic diesel operated hammer. Before commencing driving operation by rig fitted with automatic diesel operated hammer, contractor shall submit method statement for carrying out the operation including sequence of driving to the Engineer-in-charge for approval. However, engineer’s approval shall not relieve the contractor of his responsibilities and obligations under contract.

Consider 4.25 nos Pile (40'-0" each)= 51.82 meter driving in 1 day

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Hire charge of diesel hammer mounted completed rig set. Hire charge of complete rig set (Crane, Hammer, Rig, Generator etc. complete.) 1 day 25200 per day 25200 25200
4 Foreman/Supervisor Labour : Foreman 2 nos 850 per day 850 1700
5 Diesel hammer mounted rig operator Diesel operated rig driver 1 no 700 per day 700 700
6 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to rig driver 8 nos 550 per day 550 4400
7 Skilled labour Skilled labour 6 nos 600 per day 600 3600
2 Fuel, lubricant etc. LS 2500
3 Tools & plant, consumables, spares, maintenance, insurance etc. LS 500
Sub-Total 38600
Contractor's Profit 10% 0.1 3860
Contractor's Overhead Expenses 3.5% 0.035 1351
Total 43811
Add VAT with adjustment factor. 1.08108 7.5% 0.075 3552.24
Grand Total 47363.24
Rate per meter 913.99
Rate per meter 913.99