Breakup

09.22.4 Driving of 205 mm x 205 mm x 7.6 m pre-cast pile

Considering 25 rft long 7 nos pile

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Hire charge of pre-cast micro pile driving complete rig set including operational expenses Hire charge of driving equipment in/c cost of fuel and lubricant etc. 1 day 5000 per day 5000 5000
2 Pile rig operator Rig operator 1 nos 700 per day 700 700
3 Skilled labour Skilled labour 3 nos 600 per day 600 1800
4 Ordinary labour Ordinary labour 8 nos 550 per day 550 4400
Sub-Total 11900
Contractor's Profit 10% 0.1 1190
Contractor's Overhead Expenses 3.5% 0.035 416.5
Total 13506.5
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1095.12
Grand Total 14601.62
Rate per rft 83.44
Rate per rm 273.77
Help