Considering 25 rft long 7 nos pile
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Hire charge of pre-cast micro pile driving complete rig set including operational expenses Hire charge of driving equipment in/c cost of fuel and lubricant etc. | 1 | day | 5000 | per day | 5000 | 5000 | |
| 2 | Pile rig operator Rig operator | 1 | nos | 700 | per day | 700 | 700 | |
| 3 | Skilled labour Skilled labour | 3 | nos | 600 | per day | 600 | 1800 | |
| 4 | Ordinary labour Ordinary labour | 8 | nos | 550 | per day | 550 | 4400 | |
| Sub-Total | 11900 | |||||||
| Contractor's Profit | 10% | 0.1 | 1190 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 416.5 | |||||
| Total | 13506.5 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1095.12 | ||||
| Grand Total | 14601.62 | |||||||
| Rate per rft | 83.44 | |||||||
| Rate per rm | 273.77 | |||||||