Extra rate for each 1 m additional lead beyond 10 m Considering 1000 cft work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Ordinary labour Ordinary labour | 0.2 | nos | 550 | per day | 550 | 110 | |
| Sub-Total | 110 | |||||||
| Contractor's Profit | 10% | 0.1 | 11 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 3.85 | |||||
| Total | 124.85 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 10.12 | ||||
| Grand Total | 134.97 | |||||||
| Rate per cft | 0.14 | |||||||
| Rate per per cum | 4.9399999999999995 | |||||||