Breakup

09.24.1 Mobilization and demobilization to site and PIT on12(twelve) piles or less

PIT : Pile Integrity Test

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 PIT : mobilization,demobilization, accomodation +12pile PIT Mobilization & demobilization in/c 1st 12 piles 1 piles 28000 per 100km within Dhaka 28000 28000
Sub-Total 28000
Contractor's Profit 10% 0.1 2800
Contractor's Overhead Expenses 3.5% 0.035 980
Total 31780
Add VAT with adjustment factor. 1.08108 7.5% 0.075 2576.75
Grand Total 34356.75
Rate per pile 34357
Rate per pile 34357