Breakup

02.2 Bailing out of trapped water caused by inundation or rain, by pump from foundation trenches.

Bailing out water during earthwork in excavation for foundation Break-up for 4 hours use of pump in one day to discharge water

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Hire charge of diesel operated 1/4 cusec capacity water pump Hire charge of pump 1 day 640 per day 640 640
2 Diesel Fuel for 4 hours 3 liter 68 litre 68 204
3 Machine operator Pump operator 1 no 700 per day 700 700
Sub-Total 1544
Contractor's Profit 10% 0.1 154.4
Contractor's Overhead Expenses 3.5% 0.035 54.04
Total 1752.44
Add VAT with adjustment factor. 1.08108 7.5% 0.075 142.09
Grand Total 1894.53
Rate per hour 473.75
Rate per hour 11370