09.26.2.1 Driving pre-cast pile of 300 mm x 300 mm to 350 mm x 350 mm X-section made with shoe/ without shoe by Hydraulic static pile driver of upto 320 tonne (metric ton) capacity; arranged with necessary cranes, power source, maintaining driving log and record of pressure exerted on piles driven in to desired RL or capacity level ; complete in all respect including handling of piles, dressing & leveling of site, way making, surveying, layout setting etc ended with the submission of pile driving report in three copies duly signed by professional engineer and approved by the Engineer-in-charge.

Considering 13.5 nos 300 mm x 300 mm to 350 mm x 350 mm Pile (40'-0" each)= 164.584 meter driving in 1 day

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Hire charge of hydraulic static pile driver complete rig set Hire charge of complete rig set 1 per day 76200 per day 76200 76200
2 Generator, fuel, lubricant for hydraulic static pile driver Generator,Fuel, lubricant etc. 1 per day 20400 per day 20400 20400
4 Data logging engineer at hydraulic pile driver Labour : Data logging Engineer 1 no 1900 per day 1900 1900
5 Chief Mechanic, at hydraulic pile driver Chief Mechanic 1 no 1400 per day 1400 1400
6 Helper to mechanic, at hydraulic pile driver Helper to mechanic 1 no 600 per day 600 600
7 Foreman/Supervisor Foreman 1 no 850 per day 850 850
8 Crane Operator, at hydraulic pile driver Crane Operator 1 no 850 per day 850 850
9 Helper to crane operator, at hydraulic pile driver Helper to crane operator 1 no 600 per day 600 600
10 Machine Operator, at hydraulic pile driver Machine Operator 1 no 650 per day 650 650
11 Helper to machine operator, at hydraulic pile driver Helper to machine operator 1 no 600 per day 600 600
12 Generator Operator, at hydraulic pile driver Generator Operator 1 no 650 per day 650 650
13 Surveyer to pile layout , at hydraulic pile driver Surveyer to pile layout 1 no 1200 per day 1200 1200
14 Helper to surveyer, at hydraulic pile driver Helper to surveyer 1 no 850 per day 850 850
15 Skilled Labor, at hydraulic pile driver Skilled Labor 3 nos 600 per day 600 1800
16 Ordinary labour Ordinary Labour 6 nos 550 per day 550 3300
17 Compilation of driving report, pile capacity log & submission to PE on signing it on hydraulic pile driver Compilation of driving Report, Pile Capacity log & submission to PE on signing it. 1 copy 12000 per day 2000 2000
3 Maintenance, insurance etc. LS 5000
Sub-Total 118850
Contractor's Profit 10% 0.1 11885
Contractor's Overhead Expenses 3.5% 0.035 4159.75
Total 134894.75
Add VAT with adjustment factor. 1.08108 7.5% 0.075 10937.4
Grand Total 145832.15
Rate per meter 886.06
Rate per meter 886.06