Breakup

09.29 Cutting (if necessary) charge of U-type Hot rolled steel sheet piles to design length and shape as per design and specification (thickness, length and mechanical properties) and instruction by all complete as per direction of the Engineer-in-charge.

Considering Each piece (400 mm width X 12 m length)

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Hire charge of welding machine Cost of equipment (i) H.C. of Electric Auto Gas Cutter Set including Oxy-Acetylene i/c power consumption 0.18 day 750 per day 750 135
2 Welder Cost of labour (i) Welder 0.24 day 700 per day 700 168
Sub-Total 303
Contractor's Profit 10% 0.1 30.3
Contractor's Overhead Expenses 3.5% 0.035 10.61
Total 343.91
Add VAT with adjustment factor. 1.08108 7.5% 0.075 27.88
Grand Total 371.79
Rate per piece 372
Rate per per piece 372