09.31 Fabrication and construction of corner Joints in steel sheet piles including cutting, welding, shaping as per design and specification and as per requirement including supply of necessary welding materials, equipments and other accessories as per specification and direction of Engineer in charge.

Considering Each piece (400mm x 12m length)

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Electrodes including electricity Cost of materials (i) Electrode (copper) 6 pc 10 each 10 60
2 Welder Cost of labour (i) Welder 0.075 day 700 per day 700 52.5
3 Generator/ Power consumption per kwh Cost of equipment (i) Generator/ Power consumption 2 KWH 11 per kwh 11 22
4 Hire charge of welding machine Cost of equipment (ii) Welding machine 0.065 day 750 per day 750 48.75
Sub-Total 183.25
Contractor's Profit 10% 0.1 18.32
Contractor's Overhead Expenses 3.5% 0.035 6.41
Total 207.98
Add VAT with adjustment factor. 1.08108 7.5% 0.075 16.86
Grand Total 224.84
Rate per piece 225
Rate per per piece 225