Supplying and driving wooden ballah in palisading Considering 20 rft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Shal ballah (avg. dia 6") for driving Cost of ballah in/c carriage | 20 | rft | 80 | per foot | 80 | 1600 | |
| 2 | Skilled labour Labour for driving Skilled labour | 1 | no | 600 | per day | 600 | 600 | |
| 3 | Ordinary labour Labour for driving Ordinary labour | 2 | nos | 550 | per day | 550 | 1100 | |
| 4 | Ordinary labour Sundries, removing of skin, sizing and coaltaring in/c hire charge of monkey with driving arranement. | 1 | LS | 550 | per day | 412.5 | 412.5 | |
| Sub-Total | 3712.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 371.25 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 129.94 | |||||
| Total | 4213.69 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 341.65 | ||||
| Grand Total | 4555.34 | |||||||
| Rate per rft | 227.75 | |||||||
| Rate per per rm | 747.25 | |||||||