Breakup

02.4 Supplying of wooden ballah having an average diameter not less than 150 mm (without barks) at one third distance from larger end with a minimum end diameter of 100 mm for retaining purpose and driving to a depth as per design and drawing by any method including all arrangement for staging, hoisting, carrying etc. complete and accepted by the Engineer-in-charge.

Supplying and driving wooden ballah in palisading Considering 20 rft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Shal ballah (avg. dia 6") for driving Cost of ballah in/c carriage 20 rft 80 per foot 80 1600
2 Skilled labour Labour for driving Skilled labour 1 no 600 per day 600 600
3 Ordinary labour Labour for driving Ordinary labour 2 nos 550 per day 550 1100
4 Ordinary labour Sundries, removing of skin, sizing and coaltaring in/c hire charge of monkey with driving arranement. 1 LS 550 per day 412.5 412.5
Sub-Total 3712.5
Contractor's Profit 10% 0.1 371.25
Contractor's Overhead Expenses 3.5% 0.035 129.94
Total 4213.69
Add VAT with adjustment factor. 1.08108 7.5% 0.075 341.65
Grand Total 4555.34
Rate per rft 227.75
Rate per per rm 747.25
Help