Breakup

09.34 Mobilization & demobilization of joist driving rig

Considering 1 set

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Truck fare within 20 km including loading & un-loading Truck fare in/c loading and unloading 4 trips 1850 per trip 1850 7400
2 Incidental and sundries etc. LS 320
Sub-Total 7720
Contractor's Profit 10% 0.1 772
Contractor's Overhead Expenses 3.5% 0.035 270.2
Total 8762.2
Add VAT with adjustment factor. 1.08108 7.5% 0.075 710.45
Grand Total 9472.65
Rate per set per site 9473
Rate per set per site 9473