Breakup

09.35 Driving joist (up to 6.5m depth) of any sections and weights in any type of soil by mechanical device including handling and placing in position, supply of all materials and equipments related with driving of sheet piles, correcting leaning beyond tolerance and other defects etc. all complete as per direction of Engineer in charge (measurement will be taken on meter).

Consider 5 nos joist (40'-0" each)= 60.97 meter driving in 1 day

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Hire charge of pre-cast pile driving complete rig set including operational expenses Hire charge of complete rig set 1 day 6000 per day 6000 6000
4 Foreman/Supervisor Labour : Foreman 2 nos 850 per day 850 1700
5 Pile rig operator Diesel operated rig driver 1 no 700 per day 700 700
6 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to rig driver 8 nos 550 per day 550 4400
7 Skilled labour Skilled labour 6 nos 600 per day 600 3600
2 Fuel, lubricant etc. LS 3000
3 Tools & plant, consumables, spares, maintenance, insurance etc. LS 500
Sub-Total 19900
Contractor's Profit 10% 0.1 1990
Contractor's Overhead Expenses 3.5% 0.035 696.5
Total 22586.5
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1831.34
Grand Total 24417.84
Rate per meter 400.49
Rate per meter 400.49