Breakup

10.7 Supply and fabrication of built-up sections for shore piles from steel plates conforming to ASTM A36, with a minimum yield strength of 250 MPa, including the cost of testing of plates, application of red/grey-oxide primer etc. all complete as per drawing, specification and direction of Engineer-in-charge (Salvage materials shall be the contractors property after completion of the work, rate is excluding the cost of driving and taking out).

Considering 1000 kg of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 MS plate of grade 275 Mpa MS plate in/cl Wastage 2% 1020 kg 74000 per M.Ton 74 75480
2 Fabrication charge for column, beam, rafter using MS plates including the cost of electricity, LP gas, machinares etc. Cost for labour, electricity, gas etc. 1000 kg 20000 per M.Ton 20 20000
3 Local carriage, load-unload 1000 kg 1700 per M.Ton 1.7 1700
4 Labour charge for redoxide painting Labour 1000 kg 600 per M.Ton 0.6 600
5 Thinner for anti corrosive red oxide paint Thiner 4 liter 120 per litre 120 480
6 Anti corrosive red oxide paint Red oxide primer 12 liter 180 per litre 180 2160
7 MS plate of grade 275 Mpa Deduct salvage value of steel pile @ 60% on cost steel materials 1020 kg 74000 per M.Ton -44.4 -45288
Sub-Total 55132
Contractor's Profit 10% 0.1 5513.2
Contractor's Overhead Expenses 3.5% 0.035 1929.62
Total 62574.82
Add VAT with adjustment factor. 1.08108 7.5% 0.075 5073.63
Grand Total 67648.45
Rate per kg 67.65
Rate per kg 67.65
Help