10.8 Supply and fabrication of hot rolled structural grade steel Sections of any thickness conforming to ASTM A36 with a minimum yield strength of 250 MPa for shore piling , including the cost of testing , application of red/grey-oxide primer etc. all complete as per drawing, specification and direction of Engineer-in-charge( Salvage materials shall be the contractors property after completion of work, rate is excluding the cost of driving and taking out).

Considering 1000 kg of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Hot rolled W, I, S, T shape sections of grade 275 MPa MS plate in/cl Wastage 2% 1020 kg 80000 per M.Ton 80 81600
2 Fabrication charge of Hot Rolled sections for shore piles of grade 250 Mpa including the cost of electricity, LP gas, machinares etc. Cost for labour, electricity, gas etc. 1000 kg 5000 per M.Ton 5 5000
3 Local carriage, load-unload 1000 kg 1700 per M.Ton 1.7 1700
4 Labour charge for redoxide painting Labour 1000 kg 600 per M.Ton 0.6 600
5 Thinner for anti corrosive red oxide paint Thiner 4 liter 120 per litre 120 480
6 Anti corrosive red oxide paint Red oxide primer 12 liter 180 per litre 180 2160
7 Hot rolled W, I, S, T shape sections of grade 275 MPa Deduct salvage value of steel pile @ 60% on cost steel materials 1020 kg 80000 per M.Ton -48 -48960
Sub-Total 42580
Contractor's Profit 10% 0.1 4258
Contractor's Overhead Expenses 3.5% 0.035 1490.3
Total 48328.3
Add VAT with adjustment factor. 1.08108 7.5% 0.075 3918.51
Grand Total 52246.81
Rate per kg 52.25
Rate per kg 52.25