Considering 100 kg of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Grade 300(300Mpa / 300N/mm2 ≈ 43500psi/40 Grade): BDS- 6935-2006 - B300 and Ratio fy to fu =>1.25 Sag rod with 2% wastage | 102 | kg | 65000 | per M. ton | 65 | 6630 | |
| 2 | 12 mm I bolt with heal side washer and clamp | 5.5 | kg | 157 | per set | 157 | 863.5 | |
| 3 | Making thread for sag rod | 100 | kg | 13 | per Kg | 13 | 1300 | |
| 4 | Local carriage, load-unload | 100 | kg | 1700 | per M.Ton | 17 | 1700 | |
| 5 | Erection charge for roof/wall sheet including flashing and trims | 100 | kg | 8 | per Kg | 8 | 800 | |
| Sub-Total | 11293.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 1129.35 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 395.27 | |||||
| Total | 12818.12 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1039.31 | ||||
| Grand Total | 13857.43 | |||||||
| Rate per kg | 138.57 | |||||||
| Rate per kg | 138.57 | |||||||