10.14 Supply and fixing of sag rod (up to level-4) conforming to grade 40, with a minimum yield strength of 275 MPa, including the cost of making threads, nuts and washers, red oxide primer etc. all complete as per drawing, specification and direction of Engineer-in-charge.

Considering 100 kg of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Grade 300(300Mpa / 300N/mm2 ≈ 43500psi/40 Grade): BDS- 6935-2006 - B300 and Ratio fy to fu =>1.25 Sag rod with 2% wastage 102 kg 65000 per M. ton 65 6630
2 12 mm I bolt with heal side washer and clamp 5.5 kg 157 per set 157 863.5
3 Making thread for sag rod 100 kg 13 per Kg 13 1300
4 Local carriage, load-unload 100 kg 1700 per M.Ton 17 1700
5 Erection charge for roof/wall sheet including flashing and trims 100 kg 8 per Kg 8 800
Sub-Total 11293.5
Contractor's Profit 10% 0.1 1129.35
Contractor's Overhead Expenses 3.5% 0.035 395.27
Total 12818.12
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1039.31
Grand Total 13857.43
Rate per kg 138.57
Rate per kg 138.57