Considering 100 meter work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 16 mm steel wire 16 mm wire with 5% wastage | 105 | rm | 126 | per meter | 126 | 13230 | |
| 2 | 16 mm I bolt with heal side washer and clamp | 18 | set | 178 | per set | 178 | 3204 | |
| 3 | Local carriage, load-unload | 171.21 | kg | 1700 | per M.Ton | 1.7 | 291.06 | |
| 4 | Erection charge for roof/wall sheet including flashing and trims | 171.21 | kg | 8 | per Kg | 8 | 1369.68 | |
| Sub-Total | 18094.74 | |||||||
| Contractor's Profit | 10% | 0.1 | 1809.47 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 633.32 | |||||
| Total | 20537.53 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1665.2 | ||||
| Grand Total | 22202.73 | |||||||
| Rate per kg | 222.03 | |||||||
| Rate per kg | 222.03 | |||||||