Breakup

10.15 Supply and fixing of cable/wire bracing conforming to "ASTM A475" with a minimum yield strength of 1193 MPa, with I-bolt and hill side washer, all complete as per drawing, specification and direction of Engineer-in-charge.

Considering 100 meter work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 16 mm steel wire 16 mm wire with 5% wastage 105 rm 126 per meter 126 13230
2 16 mm I bolt with heal side washer and clamp 18 set 178 per set 178 3204
3 Local carriage, load-unload 171.21 kg 1700 per M.Ton 1.7 291.06
4 Erection charge for roof/wall sheet including flashing and trims 171.21 kg 8 per Kg 8 1369.68
Sub-Total 18094.74
Contractor's Profit 10% 0.1 1809.47
Contractor's Overhead Expenses 3.5% 0.035 633.32
Total 20537.53
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1665.2
Grand Total 22202.73
Rate per kg 222.03
Rate per kg 222.03
Help