Considering 1000 Kg of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Shear stud of variable dia of grade 275 Mpa 16 mm wire with 5% wastage | 1000 | kg | 126 | per Kg | 126 | 126000 | |
| 2 | Local carriage, load-unload | 1000 | kg | 1700 | per M.Ton | 1.7 | 1700 | |
| 3 | Erection charge for built-up or hot rolled sections | 1000 | kg | 9600 | per M.Ton | 10 | 10000 | |
| Sub-Total | 137700 | |||||||
| Contractor's Profit | 10% | 0.1 | 13770 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 4819.5 | |||||
| Total | 156289.5 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 12672.11 | ||||
| Grand Total | 168961.61 | |||||||
| Rate per kg | 168.96 | |||||||
| Rate per kg | 168.96 | |||||||