Considering 1000 Kg of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 0.70 mm thick GP decking sheet of Grade 345 Mpa GP sheet with 2% wastage | 1020 | kg | 127000 | per M.Ton | 127 | 129540 | |
| 2 | Decking screw/fastener Fastener | 400 | pcs | 8 | per pcs | 8 | 3200 | |
| 3 | Fabrication charge for decking panel Cost for fabrication | 1000 | kg | 9000 | per M.Ton | 9 | 9000 | |
| 4 | Local carriage, load-unload Local carriage, load-unload | 1000 | kg | 1700 | per M.Ton | 1.7 | 1700 | |
| 5 | Erection charge for decking panel Cost of Erection | 1000 | kg | 8 | per Kg | 8 | 8000 | |
| Sub-Total | 151440 | |||||||
| Contractor's Profit | 10% | 0.1 | 15144 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 5300.4 | |||||
| Total | 171884.4 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 13936.56 | ||||
| Grand Total | 185820.96 | |||||||
| Rate per kg | 185.82 | |||||||
| Rate per kg | 185.82 | |||||||