Supplying and fitting-fixing horizontal bracing in palisading with ½ split wooden ballah. Considering 20 rft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Shal ballah (avg. dia 6") for driving Cost for 1/2 split ballah in/c carriage | 20 | rft | 80 | per foot | 40 | 800 | |
| 2 | Skilled labour Labour for fitting-fixing including spliting Skilled labour | 0.25 | no | 600 | per day | 600 | 150 | |
| 3 | Ordinary labour Labour for fitting-fixing including spliting Ordinary labour | 0.25 | no | 550 | per day | 550 | 137.5 | |
| 4 | Grade 300(300Mpa / 300N/mm2 ≈ 43500psi/40 Grade): BDS- 6935-2006 - B300 and Ratio fy to fu =>1.25 Gajals, Nails and wires etc. | 1 | LS | 65000 | per M. ton | 32.91 | 32.91 | |
| Sub-Total | 1120.41 | |||||||
| Contractor's Profit | 10% | 0.1 | 112.04 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 39.21 | |||||
| Total | 1271.66 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 103.11 | ||||
| Grand Total | 1374.77 | |||||||
| Rate per rft | 68.75 | |||||||
| Rate per per rm | 225.57 | |||||||