Considering 1000 kg of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 6 mm thick ASTM A572 Chequered plate Plate with 3% wastage | 1030 | kg | 138000 | per M.Ton | 138 | 142140 | |
| 2 | Fabrication charge of chequered plate including the cost of electricity, LP gas, machinares etc. Cost for fabrication | 1000 | kg | 12000 | per M.Ton | 12 | 12000 | |
| 3 | Local carriage, load-unload Local carriage, load-unload | 1000 | kg | 1700 | per M.Ton | 1.7 | 1700 | |
| 3 | Skilled labour Labour | 1000 | kg | 600 | per day | 0.6 | 600 | |
| 4 | Thinner for anti corrosive red oxide paint Thinner | 4 | liter | 120 | per litre | 120 | 480 | |
| 5 | Anti corrosive red oxide paint Red oxide primer | 12 | liter | 180 | per litre | 180 | 2160 | |
| Sub-Total | 159080 | |||||||
| Contractor's Profit | 10% | 0.1 | 15908 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 5567.8 | |||||
| Total | 180555.8 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 14639.64 | ||||
| Grand Total | 195195.44 | |||||||
| Rate per kg | 195.19 | |||||||
| Rate per kg | 195.19 | |||||||