Considering 1000 kg of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 0.47mm colour profile sheet 0.47 mm colour sheet with carriage | 1000 | kg | 145000 | per M.Ton | 145 | 145000 | |
| 2 | Fabrication charge for roof / wall sheet Cost for fabrication | 1000 | kg | 7500 | per M.Ton | 7.5 | 7500 | |
| 3 | Local carriage, load-unload Local carriage, load-unload | 1000 | kg | 1700 | per M.Ton | 1.7 | 1700 | |
| 3 | Erection charge for roof/wall sheet including flashing and trims Cost of Erection | 1000 | kg | 8 | per Kg | 8 | 8000 | |
| Sub-Total | 162200 | |||||||
| Contractor's Profit | 10% | 0.1 | 16220 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 5677 | |||||
| Total | 184097 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 14926.77 | ||||
| Grand Total | 199023.77 | |||||||
| Rate per kg | 199.02 | |||||||
| Rate per kg | 199.02 | |||||||