Considering 150 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Carpenter Labour cost: Carpenter | 0.75 | no | 700 | per day | 700 | 525 | |
| 2 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to carpenter | 0.375 | no | 550 | per day | 550 | 206.25 | |
| 3 | Ordinary labour Ordinary labour | 0.75 | no | 550 | per day | 550 | 412.5 | |
| 4 | Bamboo Bamboo for scaffolding : using 6 times | 3 | nos | 13.5 | per foot | 45 | 135 | |
| 5 | 0.45 mm thick C.I. sheet: Galvanized C.I. sheet: Price for per sqm (4.66kg/sqm =65kg/13.94sqm=150sft) | 1 | sqm | 79000 | per M. ton | 368.14 | 368.14 | |
| 6 | 0.45 mm thick C.I. sheet: Screws, limpet, washer etc. | 1 | sqm | 79000 | per M. ton | 11.04 | 11.04 | |
| Sub-Total | 1657.93 | |||||||
| Contractor's Profit | 10% | 0.1 | 165.79 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 58.03 | |||||
| Total | 1881.75 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 152.57 | ||||
| Grand Total | 2034.32 | |||||||
| Rate per sft | 13.56 | |||||||
| Rate per sqm | 145.96 | |||||||