Breakup

10.22.1 Galvanized

Considering 9.1 (30 rft) meter. of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 0.27 mm thick 6'-0" x 18" ridging: Price considering 10% laping 10.01 rm 360 per pc 196.86 1970.57
2 0.27 mm thick 6'-0" x 18" ridging: Screws, limpet, washer etc. 10.01 rm 360 per pc 29.53 295.6
3 Carpenter Carpenter 1 no 700 per day 700 700
4 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to carpenter 1 no 550 per day 550 550
Sub-Total 3516.17
Contractor's Profit 10% 0.1 351.62
Contractor's Overhead Expenses 3.5% 0.035 123.07
Total 3990.86
Add VAT with adjustment factor. 1.08108 7.5% 0.075 323.58
Grand Total 4314.44
Rate per rft 143.8
Rate per rm 471.81