Considering 9.1 (30 rft) meter. of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 0.27 mm thick 6'-0" x 18" ridging: Price considering 10% laping | 10.01 | rm | 360 | per pc | 196.86 | 1970.57 | |
| 2 | 0.27 mm thick 6'-0" x 18" ridging: Screws, limpet, washer etc. | 10.01 | rm | 360 | per pc | 29.53 | 295.6 | |
| 3 | Carpenter Carpenter | 1 | no | 700 | per day | 700 | 700 | |
| 4 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to carpenter | 1 | no | 550 | per day | 550 | 550 | |
| Sub-Total | 3516.17 | |||||||
| Contractor's Profit | 10% | 0.1 | 351.62 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 123.07 | |||||
| Total | 3990.86 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 323.58 | ||||
| Grand Total | 4314.44 | |||||||
| Rate per rft | 143.8 | |||||||
| Rate per rm | 471.81 | |||||||