Considering 9.1 meter. (30 rft) of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 0.27 mm thick 6'-0" x 18" coloured ridging: Price considering 10% laping | 10.01 | rm | 420 | per pc | 229.67 | 2299 | |
| 2 | 0.27 mm thick 6'-0" x 18" coloured ridging: Screws, limpet washer etc. | 10.01 | rm | 420 | per pc | 34.45 | 344.84 | |
| 3 | Carpenter Carpenter | 1 | no | 700 | per day | 700 | 700 | |
| 4 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to carpenter | 1 | no | 550 | per day | 550 | 550 | |
| Sub-Total | 3893.84 | |||||||
| Contractor's Profit | 10% | 0.1 | 389.38 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 136.28 | |||||
| Total | 4419.5 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 358.34 | ||||
| Grand Total | 4777.84 | |||||||
| Rate per rft | 159.27 | |||||||
| Rate per rm | 522.56 | |||||||