Breakup

01.1.3.2 Providing necessary facilities in construction site for maintaining site safety of 10 nos construction inspection team member including safety helmet, safety goggles, safety shoe etc.

Considering 10 nos construction inspection team member

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Safety Helmet Safety Helmet 10 nos 200 each 200 2000
2 Safety Shoe 10 nos 600 each 600 6000
3 Goggles 10 nos 80 each 80 800
Sub-Total 8800
Contractor's Profit 10% 0.1 880
Contractor's Overhead Expenses 3.5% 0.035 308
Total 9988
Add VAT with adjustment factor. 1.08108 7.5% 0.075 809.84
Grand Total 10797.84
Rate per set 10798
Rate per per set 10798