Considering 10 nos construction inspection team member
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Safety Helmet Safety Helmet | 10 | nos | 200 | each | 200 | 2000 | |
| 2 | Safety Shoe | 10 | nos | 600 | each | 600 | 6000 | |
| 3 | Goggles | 10 | nos | 80 | each | 80 | 800 | |
| Sub-Total | 8800 | |||||||
| Contractor's Profit | 10% | 0.1 | 880 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 308 | |||||
| Total | 9988 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 809.84 | ||||
| Grand Total | 10797.84 | |||||||
| Rate per set | 10798 | |||||||
| Rate per per set | 10798 | |||||||