02.7.1 Shore protection work during excavation in foundation trenches up to 1.5 m depth to protect loss due to damage of property by palisading accepted by the Engineer-in-charge. [The rate is including the cost of vertical post]

considering 2 x 22'-0" x 5'-0"= 220.00 sft 2 x 12'-0" x 5'-0"= 120.00 sft 340.00 sft area of palisading

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Palesading (Item 186) Palisading 340 sft 46.4 sft 46.4 15776
2 Bamboo driving (Item 185) Bamboo for driving 2 x 5 x 8'-0"= 80.00 rft 2 x 1 x 8'-0"= 16.00 rft 96.00 rft 96 rft 22.44 rft 22.44 2154.24
3 G.I. wire 1/8" G.I. wire for anchoring: 2 x 2 x 5 x 7'-0"= 140.00 rft 2 x 2 x 1 x 7'-0"= 28.00 rft 168.00 rft = 3.21 kg 3.21 kg 120 per kg 120 385.2
Sub-Total 18315.44
Contractor's Profit 10% 0.1 1831.54
Contractor's Overhead Expenses 3.5% 0.035 641.04
Total 20788.02
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1685.51
Grand Total 22473.53
Rate per sft 66.1
Rate per sqm 711.5