Breakup

10.28 Supply and pouring of non-shrink grout to steel column bases conforming to ASTM C 109 having compressive strength not less than 45 MPa, including the cost of shutter and necessary accessories, all complete as per drawing, specification and direction of Engineer-in-charge.

for 1.0 cum work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 cost of non-shrink grout per bag (25 kg ) Cost of materials : Cost of non shrink grout 78 bag 1500 per bag 1500 117000
3 Labour charge for application of non-shrink grout including the cost of making shutter Labour charge for shuttering and application of non-shrink grout 1 per cum 50 per cft 1764 1764
2 Local carriage, load-unload(Per Truck) LS 1500
Sub-Total 120264
Contractor's Profit 10% 0.1 12026.4
Contractor's Overhead Expenses 3.5% 0.035 4209.24
Total 136499.64
Add VAT with adjustment factor. 1.08108 7.5% 0.075 11067.53
Grand Total 147567.17
Rate per cum 147567
Rate per cum 147567
Help