Considering 1 sft
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | M.S. angle, T and Z-section, Channel etc. 40x40x6mm M.S Angle:((Top 1x18x13'-8"=246.06rft+Bottom 1x18x12'-2"=219.06rft+Wall side 1x18x1'-6"=27rft+Vertical tie 1x18x1'-2"=21.06rft+Vertical tie 1x18x0'-10"=14.94rft+Vertical tie 1x18x0'-6"=9rft+Vertical tie(end)1x18x2'-4"=41.94rft+Inclined tie 1x18x4x4'-3"=306rft+Purline(horiz.portion)1x18x4x4'-3"=400rft+Purline(vertical portion)1x2x100'-0"=200rft)=1485.06rft+Add wastage5%=74.25rft)=1559.31rft)=475.25rm @2.944kg per rm=1399.14kg | 1399.14 | kg | 70000 | per M. ton | 70 | 97939.8 | |
| 2 | Grade 400/420(400Mpa / 400N/mm2 ≈ 60900psi/ 60 Grade), BDS-6935-2006, B400: and ratio fy to fu => 1.25 12 mm dia M.S bar. Inclined tie 1 x 17 x 16'-6" = 280.50 rft Hook (U) 1 x 17 x 2 x 1'-0" = 34.00 rft 314.50 rft Add wastage 5% = 15.73 rft = 330.23 rft )))= 100.65 rm @0.888 kg per rm = 89.38 kg | 89.38 | kg | 72000 | per M. ton | 72 | 6435.36 | |
| 3 | Fabrication charge for column, beam, rafter using MS plates including the cost of electricity, LP gas, machinares etc. Workshop charge: (item a(i) + a(ii) = 1399.14 + 89.38 = 1488.52 kg) Fabrication, welding, making charge etc. = 1488.52 kg | 1488.52 | kg | 20000 | per M.Ton | 20 | 29770.4 | |
| 4 | 0.45 mm thick C.I. sheet: Cost of C.I Sheet. "0.45 mm thick C.I sheet roofing. " "Over truss (horizontal portion) 1 x 100'-0"" x 12'-0"" =" 1200.00 sft "over truss(vertical portion) 1 x 100'-0"" x 1'-6"" =" 150.00 sft "0.45 mm thick CI sheet downpipe 5 x20 ft x1.5 ft =" 150.00 sft 0.45 mm thick CI sheet gutter = 300.00 sft = 1800.00 sft = 167.29 sqm | 167.29 | sqm | 700 | per sqm | 700 | 117103 | |
| 5 | 0.45 mm thick C.I. sheet: Screws, limpet, washer etc @ 3% on cost of C.I.Sheet | 167.29 | sqm | 700 | per sqm | 21 | 3513.09 | |
| 6 | Ordinary labour Erection Labour cost | 111.48 | sqm | 550 | per day | 200 | 22296 | |
| Sub-Total | 277057.65 | |||||||
| Contractor's Profit | 10% | 0.1 | 27705.77 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 9697.02 | |||||
| Total | 314460.44 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 25496.77 | ||||
| Grand Total | 339957.21 | |||||||
| Rate per sft | 339957 | |||||||
| Rate per sqm | 3659297.15 | |||||||