Breakup

10.33 Saftey net: Supplying temporary safety net (hessian cloth) around construction work place (along the height of the building) where public safety is likely to be endangered due to construction activities; which shall be supported using scaffolding around the building for brick work/ plaster; including fitting and fixing in position providing necessary anchors, wires, ties etc. all complete and accepted by the Engineer-in-charge. (Rate is excluding the cost of scaffolding)

Considering 20 m X20 m =400 sqm work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Jute hessian (for making formwork water-tight) Cost of materials : Hessian cloth with 3% wastage 412 sqm 3 per sft 32.28 13299.36
3 Ordinary labour Labour charge for fitting and fixing and removing of the same 2 nos 550 per day 550 1100
2 Local carriage, load-unload, wires and nails LS 2000
Sub-Total 16399.36
Contractor's Profit 10% 0.1 1639.94
Contractor's Overhead Expenses 3.5% 0.035 573.98
Total 18613.28
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1509.18
Grand Total 20122.46
Rate per sqm 50.3
Rate per sqm 541.43