Breakup

11.1.1.2 Size greater than 0'-2.5" x 0'-6" and upto 0'-2.5" x 0'-11" (finished)

Considering 1 No. door frame; Considering for door size: 3'-4" x 7'-0"; Wood reqd.: (2 x 7'-0" + 3'-4") x 0'-2.5" x 0'-9" = 2.703 cft (finished); = (2 x 7'-0" + 3'-4") x 0'-2.75" x 0'-9.25" = 3.059 cft (gross)

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Mehgani Cost of wood 3.059 cft 2000 per cft 2000 6118
2 Coal-tar (over timber surface) Coaltaring: 2 coats 13 sft 8.2 per sft 8.2 106.6
3 Carpenter Carpenter 0.8 no 700 per day 700 560
4 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to carpenter 0.1 no 550 per day 550 55
5 Skilled labour Labour for fitting, fixing in position 0.5 LS 600 per day 600 300
Sub-Total 7139.6
Contractor's Profit 10% 0.1 713.96
Contractor's Overhead Expenses 3.5% 0.035 249.89
Total 8103.45
Add VAT with adjustment factor. 1.08108 7.5% 0.075 657.04
Grand Total 8760.49
Rate per cft 3240.84
Rate per cum 114450.26