Supplying and laying minimum 2 mm thick geo-textile for protection of filled earth Considering 100 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 2 mm geo-textile Geo-textile in/c 7.5% wastage | 107.5 | sft | 11.33 | per sft | 11.33 | 1217.97 | |
| 2 | Ordinary labour G.I. Wire, spning etc. | 1 | LS | 550 | per day | 94.53 | 94.53 | |
| 3 | Skilled labour Labour Skilled labour | 0.25 | no | 600 | per day | 600 | 150 | |
| 4 | Ordinary labour Labour Ordinary Labour | 0.25 | no | 550 | per day | 550 | 137.5 | |
| 5 | Ordinary labour Tools and plant, sundries etc. | 1 | LS | 550 | per day | 17.19 | 17.19 | |
| Sub-Total | 1617.19 | |||||||
| Contractor's Profit | 10% | 0.1 | 161.72 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 56.6 | |||||
| Total | 1835.51 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 148.82 | ||||
| Grand Total | 1984.33 | |||||||
| Rate per sft | 19.84 | |||||||
| Rate per per sqm | 213.56 | |||||||