11.1.3.2 Size greater than 0'-2.5" x 0'-6" and upto 0'-2.5" x 0'-11" (finished)

Considering 1 No. door frame; Considering for door size: 3'-4" x 7'-0";Wood reqd.: (2 x 7'-0" + 3'-4") x 0'-2.5" x 0'-9" = 2.703 cft (finished);= (2 x 7'-0" + 3'-4") x 0'-2.75" x 0'-9.25" = 3.059 cft (gross);

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Silkarai/Chikrashi Cost of wood 3.059 cft 2500 per cft 2500 7647.5
2 Coal-tar (over timber surface) Coaltaring: 2 coats 13 sft 8.2 per sft 8.2 106.6
3 Carpenter Carpenter 0.8 no 700 per day 700 560
4 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to carpenter 0.1 no 550 per day 550 55
5 Skilled labour Labour for fitting, fixing in position 0.5 LS 600 per day 600 300
Sub-Total 8669.1
Contractor's Profit 10% 0.1 866.91
Contractor's Overhead Expenses 3.5% 0.035 303.42
Total 9839.43
Add VAT with adjustment factor. 1.08108 7.5% 0.075 797.79
Grand Total 10637.22
Rate per cft 3935.26
Rate per cum 138973.71