11.1.6.1 Upto Size 0'-2.5" x 0'-6" (finished)

Considering 1 No. door frame; Considering for door size: 3'-4" x 7'-0"; Wood reqd.: (2 x 7'-0" + 3'-4") x 0'-2.5" x 0'-5" = 1.5 cft (finished); = (2 x 7'-0" + 3'-4") x 0'-2.75" x 0'-5.25" = 1.75 cft (gross);

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Myanmar(Burma) teak Cost of wood 1.75 cft 7100 per cft 7100 12425
2 Coal-tar (over timber surface) Coaltaring: 2 coats 6.5 sft 8.2 per sft 8.2 53.3
3 Carpenter Carpenter 0.7 no 700 per day 700 490
4 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to carpenter 0.1 no 550 per day 550 55
5 Skilled labour Labour for fitting, fixing in position 0.5 LS 600 per day 600 300
Sub-Total 13323.3
Contractor's Profit 10% 0.1 1332.33
Contractor's Overhead Expenses 3.5% 0.035 466.32
Total 15121.95
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1226.1
Grand Total 16348.05
Rate per cft 10898.67
Rate per cum 384886.53