Considering 1 No. clamp.
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | M.S. plain bar and F.I. bar (non-structural use) Clamp: 1.5" x 1/4" size F.I. bar (unit wt = 1.28 lbs/rft) | 0.96 | lbs | 70000 | per M. ton | 31.75 | 30.48 | |
| 2 | Plain concrete (1:2:4) with brick chips Cost of concrete (1:2:4) | 0.1 | cft | 20151.67 | % cft | 201.52 | 20.15 | |
| 3 | Ordinary labour Labour cost | 1 | LS | 550 | per day | 49.5 | 49.5 | |
| Sub-Total | 100.13 | |||||||
| Contractor's Profit | 10% | 0.1 | 10.01 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 3.5 | |||||
| Total | 113.64 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 9.21 | ||||
| Grand Total | 122.85 | |||||||
| Rate per clamp | 123 | |||||||
| Rate per clamp | 123 | |||||||