Considering work for 1 No. frame
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | M.S. plain bar and F.I. bar (non-structural use) 1.5" x 1/4" size F.I. bar : 0.5rft ( @ 1.28 lb/rft )=0.64 Ibs | 0.64 | lbs | 70000 | per M. ton | 31.75 | 20.32 | |
| 2 | M.S. plain bar and F.I. bar (non-structural use) 2" rowel plug | 4 | nos | 70000 | per M. ton | 4.12 | 16.48 | |
| 3 | M.S. plain bar and F.I. bar (non-structural use) 2" screw | 4 | nos | 70000 | per M. ton | 5.15 | 20.6 | |
| 4 | Ordinary labour 1.5" screw | 2 | nos | 550 | per day | 5.5 | 11 | |
| 5 | Ordinary labour Cost of drilling 2" depth | 4 | nos | 550 | per day | 5.5 | 22 | |
| 6 | Ordinary labour Labour cost plus carpentry of regened | 1 | LS | 550 | per day | 16.5 | 16.5 | |
| Sub-Total | 106.9 | |||||||
| Contractor's Profit | 10% | 0.1 | 10.69 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 3.74 | |||||
| Total | 121.33 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 9.84 | ||||
| Grand Total | 131.17 | |||||||
| Rate per each | 131 | |||||||
| Rate per each | 131 | |||||||