02.10.1 Sand filling in foundation trenches and plinth with sand having F.M. 0.5 to 0.8 in 150 mm layers including leveling, watering and compaction to achieve minimum dry density of 95% with optimum moisture content (Modified proctor test) by ramming each layer up to finished level as per design supplied by the design office only, all complete and accepted by the Engineer-in-charge.

Considering 100 cft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Sand (F.M. 0.8) Sand (F.M. 0.5 to 0.8) considering additional 30% for compaction 130 cft 1670 per % cft 16.7 2171
2 Head mason / Mosaic head mistry Head mason 0.125 no 800 per day 800 100
3 Ordinary labour Labour for levelling, compacting, watering etc. 0.66666667 no 550 per day 550 366.67
4 Ordinary labour Sundries, T & P etc. 1 LS 550 per day 55 55
Sub-Total 2692.67
Contractor's Profit 10% 0.1 269.27
Contractor's Overhead Expenses 3.5% 0.035 94.24
Total 3056.18
Add VAT with adjustment factor. 1.08108 7.5% 0.075 247.8
Grand Total 3303.98
Rate per cft 33.04
Rate per per cum 1166.81