Considering 1 cft of work For Mehgoni wood
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Mehgani Cost of wood in/c 5% wastage | 1.05 | cft | 2000 | per cft | 2000 | 2100 | |
| 2 | Coal-tar (over timber surface) Coaltering: 2 coats | 14 | sft | 8.2 | per sft | 8.2 | 114.8 | |
| 3 | Nut-bolts, J-hooks etc. Cost of nuts, bolts and nails | 1 | kg | 160 | per kg | 160 | 160 | |
| 4 | Carpenter Labour for making, fitting & fixing Carpenter | 0.25 | no | 700 | per day | 700 | 175 | |
| 5 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Carpenter helper | 0.25 | no | 550 | per day | 550 | 137.5 | |
| Sub-Total | 2687.3 | |||||||
| Contractor's Profit | 10% | 0.1 | 268.73 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 94.06 | |||||
| Total | 3050.09 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 247.3 | ||||
| Grand Total | 3297.39 | |||||||
| Rate per cft | 3297 | |||||||
| Rate per per cum | 116433.55 | |||||||