Breakup

11.4.2 Mehgoni

Considering 1 cft of work For Mehgoni wood

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Mehgani Cost of wood in/c 5% wastage 1.05 cft 2000 per cft 2000 2100
2 Coal-tar (over timber surface) Coaltering: 2 coats 14 sft 8.2 per sft 8.2 114.8
3 Nut-bolts, J-hooks etc. Cost of nuts, bolts and nails 1 kg 160 per kg 160 160
4 Carpenter Labour for making, fitting & fixing Carpenter 0.25 no 700 per day 700 175
5 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Carpenter helper 0.25 no 550 per day 550 137.5
Sub-Total 2687.3
Contractor's Profit 10% 0.1 268.73
Contractor's Overhead Expenses 3.5% 0.035 94.06
Total 3050.09
Add VAT with adjustment factor. 1.08108 7.5% 0.075 247.3
Grand Total 3297.39
Rate per cft 3297
Rate per per cum 116433.55