11.5.1 Mehgoni wood stair rail

Considering, 2 x 9'-6" x 2.75" x 6.25"= 2.268 cft of work For Mehgoni wood

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Mehgani Cost of wood in/c 5% wastage 2.3814 cft 2000 per cft 2000 4762.8
2 Carpenter Labour for making rails Carpenter 1 no 700 per day 700 700
3 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Carpenter helper 0.5 no 550 per day 550 275
4 Carpenter Fitting, fixing in position in/c corner finishing Carpenter 0.5 no 700 per day 700 350
5 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Fitting, fixing in position in/c corner finishing Carpenter helper 0.5 no 550 per day 550 275
Sub-Total 6362.8
Contractor's Profit 10% 0.1 636.28
Contractor's Overhead Expenses 3.5% 0.035 222.7
Total 7221.78
Add VAT with adjustment factor. 1.08108 7.5% 0.075 585.55
Grand Total 7807.33
Rate per cft 3442.24
Rate per per cum 121562.71