Breakup

11.5.2 Chattogram Silkarai / Chikrashi wood stair rail

Considering, 2 x 9'-6" x 2.75" x 6.25"= 2.268 cft of work For Chattogram Silkarai/Chickrashi wood

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Silkarai/Chikrashi Cost of wood in/c 5% wastage 2.3814 cft 2500 per cft 2500 5953.5
2 Carpenter Labour for making rails Carpenter 1 no 700 per day 700 700
3 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Labour for making rails Carpenter helper 0.5 no 550 per day 550 275
4 Carpenter Fitting, fixing in position in/c corner finishing Carpenter 0.5 no 700 per day 700 350
5 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Fitting, fixing in position in/c corner finishing Carpenter helper 0.5 no 550 per day 550 275
Sub-Total 7553.5
Contractor's Profit 10% 0.1 755.35
Contractor's Overhead Expenses 3.5% 0.035 264.37
Total 8573.22
Add VAT with adjustment factor. 1.08108 7.5% 0.075 695.13
Grand Total 9268.35
Rate per cft 4086.42
Rate per per cum 144311.92