Breakup

11.5.3 Chattogram Teak wood stair rail

Considering, 2 x 9'-6" x 2.75" x 6.25"= 2.268 cft of work For Chattogram Teak wood

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Chattogram teak Cost of wood in/c 5% wastage 2.3814 cft 4400 per cft 4400 10478.16
2 Carpenter Labour for making rails Carpenter 1 no 700 per day 700 700
3 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Labour for making rails Carpenter helper 0.5 no 550 per day 550 275
4 Carpenter Fitting, fixing in position in/c corner finishing Carpenter 0.5 no 700 per day 700 350
5 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Fitting, fixing in position in/c corner finishing Carpenter helper 0.5 no 550 per day 550 275
Sub-Total 12078.16
Contractor's Profit 10% 0.1 1207.82
Contractor's Overhead Expenses 3.5% 0.035 422.74
Total 13708.72
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1111.52
Grand Total 14820.24
Rate per cft 6534.39
Rate per per cum 230761.98