Breakup

11.5.4 Myanmar(Burma) Teak wood stair rail

Considering, 2 x 9'-6" x 2.75" x 6.25"= 2.268 cft of work For seasoned Myanmar(Burma) Teak wood

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Myanmar(Burma) teak Cost of wood in/c 5% wastage 2.3814 cft 7100 per cft 7100 16907.94
2 Carpenter Labour for making rails Carpenter 1 no 700 per day 700 700
3 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Labour for making rails Carpenter helper 0.5 no 550 per day 550 275
4 Carpenter Fitting, fixing in position in/c corner finishing Carpenter 0.5 no 700 per day 700 350
5 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Fitting, fixing in position in/c corner finishing Carpenter helper 0.5 no 550 per day 550 275
Sub-Total 18507.94
Contractor's Profit 10% 0.1 1850.79
Contractor's Overhead Expenses 3.5% 0.035 647.78
Total 21006.51
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1703.23
Grand Total 22709.74
Rate per cft 10013.23
Rate per per cum 353617.22