Breakup

11.5.5 Jessore & other Local Teak wood stair rail

Considering, 2 x 9'-6" x 2.75" x 6.25"= 2.268 cft of work For seasoned Jessore & Other local Teak

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Jessore & other local teak Cost of wood in/c 5% wastage 2.3814 cft 3000 per cft 3000 7144.2
2 Carpenter Labour for making rails Carpenter 1 no 700 per day 700 700
3 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Labour for making rails Carpenter helper 0.5 no 550 per day 550 275
4 Carpenter Fitting, fixing in position in/c corner finishing Carpenter 0.5 no 700 per day 700 350
5 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Fitting, fixing in position in/c corner finishing Carpenter helper 0.5 no 550 per day 550 275
Sub-Total 8744.2
Contractor's Profit 10% 0.1 874.42
Contractor's Overhead Expenses 3.5% 0.035 306.05
Total 9924.67
Add VAT with adjustment factor. 1.08108 7.5% 0.075 804.7
Grand Total 10729.37
Rate per cft 4730.6
Rate per per cum 167061.14