12.4.4.2 Myanmar(Burma) Teak (Brass Fittings)

For 1 No. shutter Considering 6'-9" x 4'-8"= 31.52 sft (double leaf)

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 250 mm long brass tower bolt Fittings: 250 mm long Brass tower bolt 4 no 400 each 400 1600
2 100 mm longs brass hinge 100 mm long Brass hinge 8 no 150 each 150 1200
3 150 mm Brass handle Brass Handle 4 no 100 each 100 400
4 Brass screw/38 mm screw Brass screws 5 dzn 25 per doz. 25 125
5 Hinged cleats and buffer block Hinged cleats & buffer block 2 set 62 set 62 124
6 Carpenter Labour: Carpenter 3 nos 700 per day 700 2100
7 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Carpenter helper 4 nos 550 per day 550 2200
8 Myanmar(Burma) teak Cost of wood:(Stile 4x7"x4''x1.75'=1.36cft+Top rail 2x2'5''x4''x1.75'=0.23cft+Bottom rail 2x2'5''x9''x1.75''=0.528cft+Lockrail 2x3x23''x4''x1.75'=0.56cft+Panel 2x3x16''x23''x1.75''=2.24cft+Sash2x2(14''+21'')x0.5''x0.5'=0.02cft)=4.94cft 4.94 cft 7100 per cft 7100 35074
9 5 mm thick clear glass Cost of 5mm Glass (2 x 15'' x 22'')= 4.58sft 4.58 sft 76 per sft 76 348.08
10 Seasoning of timber in plant Seasoning of timber : Seasoning charge: 4.94 cft 165 per cft 165 815.1
11 Ordinary labour Labour for loading, unloading and carriage of timber at both ends (1 x 2) 9.88 cft 550 per day 55 543.4
Sub-Total 44529.58
Contractor's Profit 10% 0.1 4452.96
Contractor's Overhead Expenses 3.5% 0.035 1558.54
Total 50541.08
Add VAT with adjustment factor. 1.08108 7.5% 0.075 4097.92
Grand Total 54639
Rate per sft 1733.47
Rate per sqm 18659.07