Considering 1000 cft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Ordinary labour Labour for filling including local carriage | 8 | nos | 550 | per day | 550 | 4400 | |
| 2 | Skilled labour Skilled labour for dressing & consolidation | 2 | nos | 600 | per day | 600 | 1200 | |
| 3 | Ordinary labour Sundries, T & P etc. | 1 | LS | 550 | per day | 275 | 275 | |
| Sub-Total | 5875 | |||||||
| Contractor's Profit | 10% | 0.1 | 587.5 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 205.63 | |||||
| Total | 6668.13 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 540.66 | ||||
| Grand Total | 7208.79 | |||||||
| Rate per cft | 7.21 | |||||||
| Rate per per cum | 254.62 | |||||||