Breakup

12.7.2.1 Mahogany (Chemically treated by Pressure treatment method) (SS Fittings)

For 1 No. shutter Considering 6'-9" x 3'-0"= 20.25 sft (single leaf)

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 250 mm long SS tower bolt (A) Fittings: 250mm long Brass tower bolt 1 no 150 each 150 150
2 200 mm long SS socket bolt 200mm SS socket bolt 1 no 220 each 220 220
3 100 mm longs SS hinge 100mm long SS hinges 4 nos 100 each 100 400
4 Nickel plated handle Nickel plated handle 2 nos 80 each 80 160
5 SS Screws SS screws 5 dzn 30 per doz. 30 150
6 Hinged cleats and buffer block Hinged cleats & buffer block 1 set 62 set 62 62
7 Carpenter (B) Labour : Carpenter 0.5 nos 700 per day 700 350
8 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator (B) Labour : Carpenter helper 1 nos 550 per day 550 550
9 Ready made mahogany wooden shutter: minimum 36 mm thick & 400 kg/cum (c) Cost of shutter : 36 mm thick & 400 kg/cum 20.25 sft 666.75 per sft 666.75 13501.69
Sub-Total 15543.69
Contractor's Profit 10% 0.1 1554.37
Contractor's Overhead Expenses 3.5% 0.035 544.03
Total 17642.09
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1430.44
Grand Total 19072.53
Rate per sft 941.88
Rate per per sqm 10138.4