For 1 No. shutter Considering 6'-9" x 3'-0"= 20.25 sft (single leaf)
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 250 mm long SS tower bolt (A) Fittings: 250mm long SS tower bolt | 1 | no | 150 | each | 150 | 150 | |
| 2 | 200 mm long SS socket bolt 200mm SS socket bolt | 1 | no | 220 | each | 220 | 220 | |
| 3 | 100 mm longs SS hinge 100mm long SS hinges | 4 | nos | 100 | each | 100 | 400 | |
| 4 | Nickel plated handle Nickel plated handle | 2 | nos | 80 | each | 80 | 160 | |
| 5 | SS Screws SS screws | 5 | dzn | 30 | per doz. | 30 | 150 | |
| 6 | Hinged cleats and buffer block Hinged cleats & buffer block | 1 | set | 62 | set | 62 | 62 | |
| 7 | Carpenter (B) Labour : Carpenter | 0.5 | nos | 700 | per day | 700 | 350 | |
| 8 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator (B) Labour : Carpenter helper | 1 | nos | 550 | per day | 550 | 550 | |
| 9 | Ready made beech wood shutter: minimum 36 mm thick & 400 kg/cum (C) Cost of shutter: 36 mm thick & 400 kg/cum | 20.25 | sft | 1323 | per sft | 1323 | 26790.75 | |
| Sub-Total | 28832.75 | |||||||
| Contractor's Profit | 10% | 0.1 | 2883.28 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 1009.15 | |||||
| Total | 32725.18 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 2653.39 | ||||
| Grand Total | 35378.57 | |||||||
| Rate per sft | 1747.11 | |||||||
| Rate per per sqm | 18805.89 | |||||||