Breakup

02.14 Cleaning and disposing of excavated earth from the construction site by truck or by any other means to a place within 30 km radius of the city or town area including loading & unloading at both ends, leveling and dressing the carried earth etc. complete and accepted by the Engineer-in-charge.

Break-up for 1000 cft = 1150 cft loose earth

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Ordinary labour Ordinary labour for cutting, loading and unloading 7 nos 550 per day 550 3850
2 Skilled labour Skilled labour 1.5 nos 600 per day 600 900
3 5-ton capacity truck-fare including loading & unloading (within 30 km radius) Truck fare 6 trips 2300 per trip 2300 13800
4 Ordinary labour Ordinary labour for local carriage, leveling and dressing etc. 3 nos 550 per day 550 1650
5 Ordinary labour Tools and plant, sundries etc. 1 (LS) 550 per day 137.5 137.5
Sub-Total 20337.5
Contractor's Profit 10% 0.1 2033.75
Contractor's Overhead Expenses 3.5% 0.035 711.81
Total 23083.06
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1871.6
Grand Total 24954.66
Rate per cft 24.95
Rate per per cum 881.11