12.9.1 Out to out width 6.75'' and thickness 1.75'' (Hatil model no- HCL-101-101-Bch-5-88 or equivalent)

For wall finished thickness 5.75'' Hatil model no- HCL-101-101-Bch-5-88 or equivalent

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Door frame:For wall finished thickness 5.75'' Hatil model no- HCL-101-101-Bch-5-88 or equivalent Door frame 17 rft 1149 per rft 1149 19533
2 Mason / Mosaic mistry Mason 0.25 nos 700 per day 700 175
3 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Mason Helper 0.25 nos 550 per day 550 137.5
Sub-Total 19845.5
Contractor's Profit 10% 0.1 1984.55
Contractor's Overhead Expenses 3.5% 0.035 694.59
Total 22524.64
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1826.32
Grand Total 24350.96
Rate per rft 1432.41
Rate per running metre 4698.3