For wall finished thickness 5.75'' Hatil model no- HCL-101-101-Bch-5-88 or equivalent
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Door frame:For wall finished thickness 5.75'' Hatil model no- HCL-101-101-Bch-5-88 or equivalent Door frame | 17 | rft | 1149 | per rft | 1149 | 19533 | |
| 2 | Mason / Mosaic mistry Mason | 0.25 | nos | 700 | per day | 700 | 175 | |
| 3 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Mason Helper | 0.25 | nos | 550 | per day | 550 | 137.5 | |
| Sub-Total | 19845.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 1984.55 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 694.59 | |||||
| Total | 22524.64 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1826.32 | ||||
| Grand Total | 24350.96 | |||||||
| Rate per rft | 1432.41 | |||||||
| Rate per running metre | 4698.3 | |||||||